Cost Controls Report

Monitor budget performance with focus on labor hours and material costs across all production projects.

Accessing the Report

Reports > Production > Cost Controls

Report Columns

ColumnDescription
PIDProject ID (linked to project)
ClientClient name (Last, First format)
PMAssigned Project Manager
LeadLead Carpenter assigned
% Compl.Project completion percentage
Hours Used / ScopeActual hours vs. estimated hours
Hours Used %Percentage of labor budget consumed
Total Est. Material CostBudgeted material costs
Current PO CostTotal from purchase orders
Material Cost %PO costs as percentage of budget

Available Filters

Access filters by clicking Show Filters button:

FilterDescription
Project ManagerFilter by assigned PM
Lead CarpenterFilter by lead
Project Start DateStart/end date range
Opportunity TypeProject category
Production StageCurrent production stage

Quick Year Filters

Click year buttons to quickly set date range:

  • Previous year
  • Current year
  • Next year

Clear Filters

Click Clear All Filters to reset all selections.

Reading the Report

Hours Analysis

The Hours Used / Scope column shows:

Actual Hours Worked / Total Estimated Hours

Example: 45.5 / 60.0 means 45.5 hours used of 60 estimated.

The Hours Used % shows this as a percentage:

Hours Used % = (Actual Hours ÷ Estimated Hours) × 100

Material Analysis

The Material Cost % shows purchase order costs vs. budget:

Material Cost % = (PO Costs ÷ Estimated Material Cost) × 100

Visual Indicators

Red text appears when:

  • Hours Used % exceeds 100%
  • Material Cost % exceeds 100%

This highlights projects running over budget.

Sorting

Click any column header to sort:

  • Click once for ascending
  • Click again for descending
  • Sorted column is indicated visually

Key Metrics Explained

% Complete

Based on project progress tracking:

  • Updated by project manager
  • Reflects physical completion
  • May differ from cost-based completion

Hours Used %

Labor budget consumption:

  • Under 100%: On or under labor budget
  • At 100%: Exactly on budget
  • Over 100%: Over labor budget

Material Cost %

Material budget consumption:

  • Compares actual POs to estimated materials
  • Doesn't include materials not yet ordered
  • May show under 100% if POs pending

Export Options

Click Export CSV to download:

  • All visible columns
  • Filtered results only
  • For spreadsheet analysis

Common Use Cases

  1. Weekly production meeting: Review over-budget projects
  2. Project manager oversight: Check PM's portfolio status
  3. Lead carpenter review: Monitor crew performance
  4. Early warning system: Catch budget issues early

Analysis Tips

Healthy Patterns

  • Hours Used % roughly equals % Complete
  • Material Cost % tracks with project progress
  • Consistent patterns across similar projects

Warning Signs

  • Hours Used % significantly ahead of % Complete
  • Material Cost % spiking unexpectedly
  • Projects at 50% complete but 80% of hours used

Actions for Over-Budget Projects

  1. Review daily logs for issues
  2. Check for scope creep
  3. Verify time is logged correctly
  4. Discuss with PM and lead
  5. Consider change order if scope increased

Tips

  • Review at least weekly during production
  • Sort by Hours Used % to find problem projects quickly
  • Compare similar project types for benchmarking
  • Use with Daily Log Report for detail investigation